KURA Proposes Upgrading 12 Roads Under Multi-Billion-Shilling World Bank Project

The Kenya Urban Roads Authority (KURA) is proposing to upgrade 12 roads in Meru County, expanding connections around Meru Municipality.

The named routes, according to a notice issued on November 24, include KeMU-Kambakia roads, Runogone roads, Hospital roads and Western Bypass-Mate roads, alongside other short-distance links in the project area.

The scope also identifies link roads such as Runogone-Kaithe, Three Steers-Kambakia, Eastern Bypass-Hospital and connections between KeMU, Kambakia and C91.

The works will bring gravel and earth roads to bitumen standard.

Construction workers at the Wikililye–Katulani Road site in Kitui during a KeNHA inspection, September 25, 2026.

Photo

KeNHA

"The proponent, Kenya Urban Roads Authority, proposes to upgrade 12 short-distance roads (KeMU-Kambakia roads, Runogone roads, Hospital roads and Western bypass mate roads) from gravel and earth surface to bitumen standard, cross-drainage structures, 2No foot bridges, a concrete batching plant ,other associated amenities and facilities in Meru Municipality, Imenti North Sub-County, Meru County," NEMA stated.

The proposed package includes cross-drainage structures, two footbridges and a concrete batching plant, together with facilities needed to complete the road works.

The upgrade is backed by World Bank financing under the Horn of Africa Gateway Development Project, linking existing bypass sections around Meru town, expected to cost close to Ksh4.5 billion.

NEMA has received an Environmental and Social Impact Assessment (ESIA) report, which stated that the project could pose significant environmental impacts such as noise, dust, water contamination and soil erosion.

It identifies 15 noise-sensitive and 20 air-sensitive receptors, thus recommending daytime construction, advance public notices, water spraying and covered material trucks.

Additionally, it flags possible displacement, business disruption and livelihood losses, calling for a resettlement plan and fair compensation before affected people are moved.

Safety measures for the residents in the affected zones encompass temporary signs, pedestrian walkways, protective equipment for workers, traffic marshals, and proper construction debris management.

NEMA has since invited members of the public to submit written or oral comments within 30 days of publication, which are to be e-mailed to info@nema.go.ke.

An image of World Bank offices.

Photo

Print

Share this story WhatsApp Facebook X
Originally published by Kenyans.co.ke
View on Kenyans.co.ke

Comments 0

No comments yet. Start the conversation.

Loading the next story…