Nigeria’s proposed $78.5 billion investment pipeline, covering 65 projects across five sectors and potentially generating 366,763 jobs, offers an opportunity to address its infrastructure deficit. But before celebrating these ambitions, the government must confront a harder question: why does a country that commits substantial resources to infrastructure struggle to turn expenditure into functioning public assets?
The answer will help determine whether the pipeline attracts sustainable capital or becomes another collection of promises awaiting delivery. Investors will examine not only the scale of proposed projects but also Nigeria’s ability to prepare viable investments, provide predictable funding, enforce contracts and ensure infrastructure delivers the returns used to justify its financing.
“A project should not be deemed successful because a contract has been awarded, money released or equipment delivered. Success must be measured by whether the intended service is available, reaches its beneficiaries and remains functional.”
A recent BusinessDay investigation associated nearly $857 million committed to four externally financed federal projects with abandoned infrastructure, incomplete programmes or services that failed to achieve their intended outcomes. They included a dormant national security communications network, rural electricity installations that did not provide reliable power, an urban water programme that fell short and an incomplete rural telephony project.
The $857 million should not be presented as money stolen or entirely lost. The projects differ in their financing, disbursements and implementation outcomes. Nevertheless, they expose a weakness in public investment: securing finance and installing equipment do not necessarily deliver services.
A $7.5 million rural electrification intervention covering 72 communities across Enugu, Cross River and Ogun states involved installing transformers, poles and other infrastructure. Yet investigations found communities where equipment remained unused and residents still lacked reliable electricity. The government had installed assets, but beneficiaries had not received the service that justified the expenditure.
A project should not be deemed successful because a contract has been awarded, money released or equipment delivered. Success must be measured by whether the intended service is available, reaches its beneficiaries and remains functional.
Nigeria’s budgeting practices compound this weakness. In December 2025, the Federal Government directed ministries, departments and agencies to carry 70 per cent of their 2025 capital allocations into 2026, citing revenue constraints and the need to complete ongoing projects. The implementation period for outstanding capital commitments was subsequently extended.
There is a sound fiscal case for protecting viable ongoing projects rather than spreading scarce resources across new ones. But repeated rollovers expose weaknesses in project preparation, revenue forecasting and funding discipline. Contractors face uncertainty, costs can rise, and communities wait longer for services. Where projects are debt-financed, the country may continue paying financing costs while infrastructure remains incomplete or underused.
Multiyear projects are not inherently wasteful. The failure occurs when governments approve them without credible funding commitments and then rely on successive budget extensions to sustain them. Annual budgeting must not disguise the gap between political ambition and available resources.
The problem extends beyond the federal government. Tracka’s September 2026 second-quarter scorecard, based on physical monitoring of 944 projects across 29 states and the Federal Capital Territory, reported approximately ₦608.99 billion in disbursements. Of this, ₦13.86 billion was associated with projects for which monitors found no corresponding implementation. The findings concern a monitored sample, not all state projects. Financial releases, contractor payments and independently verified physical progress must also be distinguished.
Behind these outcomes is a political economy that often rewards project announcements more visibly than completion. New administrations have incentives to introduce projects carrying their names, while inherited schemes can lose political attention. Projects may enter budgets before land acquisition, feasibility, procurement or maintenance arrangements are settled. Agencies may face few consequences for delays, cost escalation or weak supervision.
This encourages project selection based on political visibility rather than economic priority. The costs extend beyond abandoned facilities: scarce resources are tied up, productivity is weakened and borrowing pressures rise, leaving less room for health, education and other essential services. When infrastructure fails to generate expected economic activity, government also loses the revenue and productivity gains that should have followed.
Nigeria must reform the incentives and institutions governing public investment.
First, no major project should enter an implementation budget without an approved feasibility study, verified land availability, realistic costing, environmental and social assessments, financing commitments and an identified operating agency. The sponsoring ministry must also demonstrate how the asset will be maintained. Projects that fail these tests should not proceed simply because they have political backing.
Second, federal and state governments should establish prioritised infrastructure pipelines. Projects should be ranked by economic returns, social benefits, regional connectivity, employment potential and fiscal affordability. Existing projects should undergo independent reviews to determine whether they should be completed, redesigned or terminated. This would prevent scarce resources being scattered across too many schemes.
Third, multiyear funding must be credible. Legislatures should scrutinise major capital commitments against realistic revenue projections and financing plans. Once a viable project is approved, the government should publish a funding schedule and disclose shortfalls that threaten delivery. New commitments should not routinely displace viable ongoing projects.
Fourth, governments should maintain public registers of major infrastructure projects, disclosing locations, contract values, contractors, funding sources, amounts released, milestones, revised costs, completion dates and operational status. Agencies should update them quarterly, separating allocations and payments from verified physical progress. Auditors and legislative committees should use the information to investigate unexplained delays, cost variations and payments unsupported by certified work.
Fifth, payments should be tied to independently verified milestones. Contract variations and extensions must be justified, while procurement authorities should enforce penalties for unjustified delays and defective work. At handover, independent technical assessments should confirm that facilities are safe and capable of providing their intended services.
Finally, maintenance must be part of the original investment. Every major project should have a named operating agency, a costed maintenance plan and an identified funding source. Annual delivery reports should show which projects were completed, became operational, were delayed or abandoned, explain failures and identify corrective action.
The $78.5 billion pipeline will mean little unless Nigeria demonstrates that it has learnt from previous projects. Investors need predictable regulation, transparent procurement, enforceable contracts and confidence that government will honour its obligations. Citizens need infrastructure that works.
Nigeria’s most urgent deficit is not simply finance. It is the institutional capacity to select the right projects, fund them realistically, execute them competently and maintain them. Until delivery matters more to government performance than announcements, every new investment pledge will face the same test: not how much Nigeria intends to spend, but how much functioning infrastructure its citizens and businesses actually receive.
- AI impersonation could become Nigeria’s biggest banking fraud threat in 2027
- Dangote Cement rewards 35 drivers as road accidents decline by 60%
- Senate aide alleges gun-butt assault by security at Appropriations meeting

No comments yet. Start the conversation.