The National Land Commission (NLC) has clarified its role in compensating landowners affected by the construction of the Isiolo-Mandera highway after the World Bank raised concerns over delays in compensation along the route.
In a statement on Wednesday, November 18, NLC dismissed the blame being directed at it, maintaining that the majority of the work, which includes processing and disbursing compensation funds for affected landowners, is undertaken by the Kenya National Highways Authority (KeNHA) as directed by the World Bank.
According to the Commission, it is only mandated to conduct land valuations, verify assets, and prepare compensation schedules.
"The National Land Commission (NLC) wishes to clarify media reports regarding concerns raised by the World Bank over alleged delays in land valuation and compensation of Project Affected Persons (PAPs) under the Horn of Africa Gateway Development Project (HOAGDP)," NLC stated.
Ardhi House
Photo
Ministry of Lands, Public Works, Housing, and Urban Development
"It is worth noting that the Commission is only engaged in undertaking valuations and development of compensation schedules, with the role of processing of funds and disbursement of compensation funds to the PAPs being done by KeNHA as per World Bank directive and implementation of the HOAGDP," it added.
In a letter directed to Treasury Cabinet Secretary John Mbadi, Roads and Transport CS Davis Chirchir, and Lands CS Alice Wahome, Kenya's World Bank Division Director Qimiao Fan said land compensation has delayed the 740-kilometre highway and has increased the risk of further cost over the allocated amount.
According to the Bank, the project was losing over Ksh1.2 billion monthly in extra costs as construction could not proceed as planned because contractors have not received unrestricted access to the land.
The global bank also identified several sections that have been affected by delayed compensation, revealing that only 1,281 project-affected persons had been compensated out of 1,669 persons.
In response, NLC revealed that it has so far conducted asset verifications for different sections of the highway and has made compensations of up to Ksh1.3 billion.
Along the Isiolo–Kulamawe–Modogashe section, the commission said payments are currently ongoing, with KeNHA awaiting the World Bank's no-objection approval for payments to 1,280 PAPs amounting to Ksh554.9 million.
For the Wajir–Kotulo section, NLC has approved compensation of 1,619 affected persons amounting to Ksh824 million. At the same time, Ksh497 million has been approved for 296 PAPs for the Isiolo-Kachuru section.
Meanwhile, the Commission has already conducted asset verification involving more than 1,105 PAPs along the Dimu-Elwak section, with Valuation expected to be completed by the end of November 2026.
"These milestones demonstrate the Commission's continued commitment to progressing land acquisition and compensation processes under the project," NLC said.
However, the Commission raised concerns over ongoing legal battles over compensation as the main reason for delaying the construction of the multibillion highway project, alongside insecurity, uncollected compensation offers and landowners that could not be traced.
The 740-kilometre highway under the Horn of Africa Gateway Development Project is 60 per cent complete as of October 26, and was initially scheduled for completion by January 2028. The timeline, however, was later pushed by the bank to around 2030.